You're reading the public documentation. Links to screens inside PrintERP will ask you to sign in first.

Adding a machine

Register a printer, cutter or laminator — and why production speed matters more than it sounds.

A machine is any piece of equipment you want to schedule work on or maintain: presses, cutters, laminators, binders. Registering one lets jobs be assigned to it, gives you time estimates, and starts its maintenance clock.

The fields

FieldWhat to put
NameWhat staff call it — “Ryobi 522”, “Front Digital”. Required.
TypeFree text: Offset Press, Digital Printer, Guillotine, Laminator.
Production SpeedPieces per hour, e.g. 10,000 sheets/hr.
Seconds per PieceRead-only. Worked out for you.
Is a printerTurns on the ink tank section.
Maintenance scheduleBy months or by pieces produced — see Maintenance.

Production speed and why it matters

You enter a speed in pieces per hour and PrintERP derives seconds per piece from it — 3600 ÷ pieces per hour. A press rated at 1,200 pieces an hour becomes 3 seconds a piece.

The field is free text and only the leading number is read, so 10,000 sheets/hr and 10000 both work. The derived figure updates as you type, so you can see the result before saving.

Why enter a speed at all

It is the only input to every time estimate: how long a run will take, the progress ring on the production floor, the time remaining, and the “probably done” flag. A machine with no usable speed simply produces no estimate — PrintERP says so rather than showing a fabricated zero.

Tip

Use your realistic throughput, not the manufacturer's headline figure. Rated speeds exclude plate changes, make-ready and reloading. A number that matches your day gives estimates you can plan around.

Printers and non-printers

Leave the printer toggle on for anything that lays down ink, and set up its ink tanks. Turn it off for cutters, laminators and binders — they schedule and maintain exactly the same way, they just have no ink to track.

After adding

Note

The Free plan allows one machine, Press five and Production fifty. See Plans and limits.